Prime Power for Pilbara Crushing Plant
The Challenge
Required reliable power to operate remote crushing plant.
Primero was in need of reliable, grid-like running power to run day-to-day operations at the crushing plant. Power sources also needed to be able to withstand the hot, dusty Pilabara conditions.
PROJECT FACT FILE
-
4x 500kVA
Prime Power Generators
-
1x 15,000L
Fuel tank
The Solution
The installation of four custom prime power generators & a 15,000L fuel tank.
Blue Diamond Machinery supplied 4 custom built 500kVA prime power generators & a 15,000 L fuel tank. Complete with USA built Cummin QSX18-G8 engine, Stamford HCI544D alternator, 500kVA/400kW prime power and 550kVA/440kW standby power, the crushing plant had ongoing prime power to ensure daily operations.
The Outcome
Reliable Prime Power for Successful Operation of Remote Crushing Plant.
The installation of generators ensured Primero met the construction and operation requirements of the crushing plant and supplied robust, reliable power for ongoing operation.